Bözberg 3 16-9

cablex is preparing the escape routes in the Bözberg tunnel.

The new, double-track Bözberg tunnel is now in operation. The old Bözberg tunnel is now being converted into a rescue tunnel. As Implenia's subcontractor, cablex is responsible for the complete preparation of the five cross passageways. From 2022, they will be used as escape routes in the event of a fire.

Carolin Rabea Primerova 1-1
01.12.2021
Author Carolin Rabea Primerova

cablex is preparing the escape routes in the Bözberg tunnel.

It is already my second visit to the Bözberg tunnel. My first visit in June 2019 was almost two and a half years ago. At that time, cablex project manager, Urs Waldner, led me through the new 2.7-kilometre-long double tunnel with the illuminated handrail, showed me the alarm units and the five cross passageways, each with two identical technical rooms. Among other things, they have a raised floor, a transformer, a 980-volt power supply cabinet, 400-volt sub-distribution, a fire alarm system and even a control system for the illuminated handrail and a connection to the SBB control system.

Upgrading of the service and rescue tunnel.

In June 2019, the tracks had not yet been laid in the new tunnel. Now, two and a half years later, trains are already rolling through the double-track tunnel. The old railway tunnel has since been shut down and converted into a service and rescue tunnel. The work is in full swing. Implenia has already dismantled the tracks and overhead lines and installed a tarred roadway. The cross passageways between the new and old tunnels have now be cut through completely. cablex is installing the lighting and the power supply in these passageways, and a lot has been done already

I am pleased that project manager Urs Waldner is once again spending some time with me, even though the completion of a construction stage is imminent: The approval inspection of the ventilation ducts in the technical rooms. As the technical rooms are located in the cross passageways and are often not entered for extended periods of time, the ventilation should ensure that the CO2 concentration does not rise too high. On the day of my visit, the final tests are already underway.

Why is the ventilation system so important?

If an accident occurs in the Bözberg tunnel, the illuminated handrail guides passengers to the emergency exits with the escape route doors. From there, passengers enter the old Bözberg tunnel, which now serves as a rescue tunnel, through the cross passageways.

cablex is installing an airlock system with motorised gates and doors at both ends of the rescue tunnel. There is another large ventilation system has been installed on both sides. This creates overpressure in the service and rescue tunnel. "In the event of a fire, the overpressure ensures that the escape route remains free of smoke so that passengers can get out of the tunnel safely," explains project manager Urs Waldner.

Other activities of cablex in the Bözberg tunnel.

Over a distance of 2.5 kilometres, cablex is installing the lighting in the rescue tunnel as well as the escape route signals. The rescue tunnel lighting is triggered when an alarm button is pressed or the escape route door is opened in the railway tunnel.

The installation work being carried out by cablex is scheduled to be completed by the end of 2021. The inspection and approval procedure for the installations will take place in January 2022, and the handover of the tunnel to the SBB will take place in April 2022.

Infobox

The Bözberg tunnel is the largest single project of the four-metre corridor on the Gotthard axis. The expansion means that semi-trailers with a corner height of four metres can also be transported by rail. The expansion will make it possible to transport goods by rail from Hamburg to Genoa.

Some figures regarding cablex’s assignment:

  • Equipment for a total of 11 technical rooms, 2 railway engineering buildings, 2 airlocks
  • 5500m illuminated handrail
  • 8000m 980V energy supply cable
  • 12 000m ribbon cable
  • 5000m ground cable
  • 20 000m of various low voltage and installation cables
  • 3000m cable routes
  • 650 LED lamps
  • 11 400-V power supply units (switchgear combinations)
  • 11 980-V supply cabinets
  • 10 22-kVA transformers
  • 2 16-kVA transformers
  • 2 132-kVA transformers
  • 5 motorised cross passageway doors and 4 airlock gates
  • Cooling-/air conditioning units
  • Painting work
  • Escape route signs and escape route lighting
  • Fire alarm system
  • Connection to the SBB control system LSS-CH
  • Ventilation system for escape routes
Begehung der Kellerräume und Teambesprechung

28 single-family homes connected in three days – Optical fibre project in Gibswil.

Unique optical fibre project in three days. Experienced team ensured fast and customer-orientated implementation.

Martina Strazzer 1-1
Field Service Techniker mit Smart Meter in der Hand vor seinem E-Auto

Major order for BKW: Together for the energy transition.

cablex electricians will replace five hundred smart meters daily for BKW by 2028.

Martina Strazzer 1-1
Praxistest SAR App 3-4

Efficient optical fibre connection: This is how the technical inspection is carried out.

Insights into the technical inspection by a cablex technician – these steps are necessary for a successful optical fibre connection.

Larissa Mihalik 1-1
Beleuchtete Autobahn bei Nacht_24-9.jpg

Transport.

Creating a future-proof infrastructure with cablex.

Field Service Techniker vor seinem E-Auto

Versatile – diverse – in high demand.

Discover how our experienced technicians address customer concerns in Switzerland on a daily basis.

Martina Strazzer 1-1
Monteur bei der Installation eines Batteriespeichers.

Battery storage for photovoltaics – Advice from cablex.

Which battery storage size is right for your business? cablex advises corporate clients on efficient and cost-effective PV storage solutions.

Carolin Rabea Primerova 1-1
Site Acquisition Report App
cablex Academy 24-9

cablex Academy.

The cablex Academy teaches specialist skills (competences) in the fields of network construction, service and installation. Here, focus is on the area of network construction for telecommunication.

Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

Montage PV Modul

Convincing pilot projects: findings from two PV system installations.

Find out how companies can increase their autonomy and use electricity more efficiently with intelligent planning and state-of-the-art technology.

Carolin Rabea Primerova 1-1
Ponton mit Glasfaserkabeln

New underwater cable secures infrastructure.

Storms and debris threaten a fibre optic cable in Lake Lugano: mud at the mouth of the river impairs its function - urgent replacement required!

Carolin Rabea Primerova 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444