The major contract with cablex described here includes the installation of over 400,000 intelligent electricity meters, known as smart meters, by the end of 2028. That amounts to around 500 meter changes per day. cablex was selected by BKW Energie AG back in 2024 as the partner for the installation of the household meters. The order encompasses the entire area served by the energy supplier.
We have over 40 technicians on the road throughout Bernese Oberland, Bernese Mittelland, Oberaargau/Solothurn and Jura/Seeland replacing electricity meters in private households and businesses. The coordination of this large-scale installation project requires careful planning and logistical precision, and every installation must comply exactly with the technical specifications and safety standards.
A meter change usually takes no longer than an hour, depending on the circumstances, and entails a brief power interruption of around 15 minutes during installation. Our technical teams have been trained by BKW to meet their needs and standards, while the technical expertise and solid dedication are supplied by our colleagues themselves.
Notification process (scheduling team).
It is important to choose a suitable time window for the installations that minimises disruption to customers' daily routines. Written notification is sent by our scheduling team one to three-and-a-half weeks before the visit, and requests for postponements are coordinated by the scheduling department.
Estevam de Menezes, electrical fitter at cablex, takes us to his "workplace in the basement of an apartment block in Ostermundigen, BE":
Major order for BKW: Together for the energy transition.
Marco Schümperli is the overall project manager for the BKW rollout at cablex. He is delighted with the way the project is going:
Thanks to the great team spirit and the highly motivated employees across all roles (scheduling, project management, installation), the project is running successfully and according to plan. The cooperation with BKW is going very well, and I particularly appreciate the open, direct and constructive communication.
Marco Schümperli, overall project manager for the BKW rollout at cablex.
Peter Flückiger, Head of Order and Master Data Management at BKW, also has very positive words to say about the cooperation with our teams:
Customer statement from BKW.
cablex is helping to ensure that both energy suppliers and consumers will be able to read off their electricity consumption digitally to the nearest quarter of an hour in future. This can be helpful in identifying power guzzlers and optimising a household's energy consumption. We are proud to be able to help shape the energy infrastructure of the future.