20210507_11172716-9.jpg

Civil work tests and validates the shotcrete 3D printing process.

The man, the dog, the house in miniature, all created with a 3D printer – a familiar sight for us today. But what about a shotcrete 3D robot? cablex sees potential in this technology to provide the infrastructure required for network construction even faster.

Carolin Rabea Primerova 1-1
18.06.2021
Author Carolin Rabea Primerova

New shaft construction and reconstruction with shotcrete printing construction technology.

When carrying out network construction, it is always necessary to rebuild or reconstruct shafts.  cablex has tested and validated a new process technology that integrates the automation and robotics of shotcrete 3D printing. The shortcrete technology from MOBBOT, which cablex tested, allows wall reinforcements and new shafts to be produced individually and made-to-measure. The dimensions can be transmitted traditionally as drawings or created using an online configurator. An automated robot system spays the walls layer by layer. A wall reinforcement can be produced within 30 minutes and used on site after 24 hours.

The wall reinforcement is placed on top of the existing shaft, meaning that only the lateral compaction needs to be restored on site. Once this is done, the shaft frame can be put on and sealed. The conventional encasing work for concreting is eliminated and the resources consumption minimised.

01_Werkleitungsbau testet 3-D-Spritzbetondruck

When does it make sense for cablex to use it?

Whether shotcrete 3D printing makes sense depends on the quantity of wall reinforcements or shafts and their design. The method can save time from an order quantity of four elements. Due to the flexibility of 3D printing, recesses for cables and a gradient can be factored in directly during production. This means that the method is also suitable for use in more complex installations. 

Time comparison with traditional methods.

cablex uses two different production methods: The first is to place the shaft frame on sand-lime bricks and then concrete it. The second traditional shaft construction variant involves first concreting a wall reinforcement, onto which the shaft frame is placed in the next step.

Using conventional methods, a total of eight hours (two half days) are spent on forming, pouring and concreting. After the concrete has cured, the shaft frame and cover are applied. The employees then compact the remaining cavities with concrete. The wall thickness with this method is 20 centimetres.

02_Werkleitungsbau testet 3-D-Spritzbetondruck

In MOBBOT’s experience, it takes an average of between half an hour and an hour to install a 3D spray-printed wall reinforcement, including assembly of the shaft frame. This means that up to four shafts can be completed per day. The possibility of supplying wall reinforcements together with the associated shaft frames also offers savings potential in terms of transport routes.

The time required for excavation and restoration is comparable for the conventional and 3D methods. The printed wall reinforcement method requires a larger excavation (approximately twice the excavation for lateral backfilling and compaction). At the same time, MOBBOT says that shotcrete 3D printing uses around 25 per cent less concrete.

This method offers the greatest potential in rollout projects where several shafts have to be completed per week.

Urs Ringgenberg Aikido Header 24-9

A philosophy that can be transferred.

He knows how to positively influence energy flows, interact with people and defend himself. In this episode of "Insights – our executive management up close and personal", we introduce you to our Chief Financial Officer.

Larissa Mihalik 1-1
Vater-und-Sohn-16-9

When two passionate people say "YES" to cablex

Cirilo's 15-year-old son, Ruben, made a conscious decision in favour of an apprenticeship at cablex.

Carolin Rabea Primerova 1-1
Freileitungskurs_Hero 3-4

A training course with lots of action!

"A super course day", which demanded the full concentration and attention of colleagues in the FS-C-12 overhead line team

Martina Strazzer 1-1
Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

24-9-NeuKinderspital

Spectacular dismantling of a lattice mast from 1914.

Under the project management of cablex, a lattice mast that is more than 100 years old is cut from the foundation with an angle grinder and transported away by helicopter.

Carolin Rabea Primerova 1-1
Solvita 24-9

We don't just talk about it ...

We don't just talk about it, we actually work for social inclusion. The Solvita Foundation in Urdorf produces cable connections for cablex that are used for smart meters.

Larissa Mihalik 1-1
Header cablex als wichtige Stütze im Swisscom Shop Rollout 3-4

cablex as a key element in the Swisscom Shop rollout.

Shopping Arena, St. Gallen. It is the 18th Swisscom Shop to be converted by the cablex electrical department based in St. Gallen. The team designed the entire electrical installation in the shop according Swisscom's new Retina concept.

Larissa Mihalik 1-1
DSC_796424-9.jpg

Taster days at cablex.

Come and see for yourself! Register for a taster session for the Certified Network Electrician (VET), Certified Electrician (VET) or Certified Assembly Electrician (VET) apprenticeships.

DSC_8480_24-9.jpg

Certified Electrician (VET).

No matter whether it's for electricity, telephony, internet or TV/radio in commercial or industrial buildings, as an installation professional you bring the nervous system inside buildings to life! Take your first step into the world of work at cablex.

Header Francesco 24-9

Ready to deliver top performance every day.

He is on the ball, motivated and ready to advance at full speed. This time, in "Insights – our executive management up close and personal", we would like to introduce you to Francesco Castelletti, Head of Field Services.

Larissa Mihalik 1-1
Grossbaustelle Schwamendingen

The watchful eye in the night.

cablex is responsible for the installation management of the operating and safety equipment on the night shift.

Carolin Rabea Primerova 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444