20210507_11172716-9.jpg

Civil work tests and validates the shotcrete 3D printing process.

The man, the dog, the house in miniature, all created with a 3D printer – a familiar sight for us today. But what about a shotcrete 3D robot? cablex sees potential in this technology to provide the infrastructure required for network construction even faster.

18.06.2021
Author Carolin Rabea Primerova

New shaft construction and reconstruction with shotcrete printing construction technology.

When carrying out network construction, it is always necessary to rebuild or reconstruct shafts.  cablex has tested and validated a new process technology that integrates the automation and robotics of shotcrete 3D printing. The shortcrete technology from MOBBOT, which cablex tested, allows wall reinforcements and new shafts to be produced individually and made-to-measure. The dimensions can be transmitted traditionally as drawings or created using an online configurator. An automated robot system spays the walls layer by layer. A wall reinforcement can be produced within 30 minutes and used on site after 24 hours.

The wall reinforcement is placed on top of the existing shaft, meaning that only the lateral compaction needs to be restored on site. Once this is done, the shaft frame can be put on and sealed. The conventional encasing work for concreting is eliminated and the resources consumption minimised.

When does it make sense for cablex to use it?

Whether shotcrete 3D printing makes sense depends on the quantity of wall reinforcements or shafts and their design. The method can save time from an order quantity of four elements. Due to the flexibility of 3D printing, recesses for cables and a gradient can be factored in directly during production. This means that the method is also suitable for use in more complex installations. 

Time comparison with traditional methods.

cablex uses two different production methods: The first is to place the shaft frame on sand-lime bricks and then concrete it. The second traditional shaft construction variant involves first concreting a wall reinforcement, onto which the shaft frame is placed in the next step.

Using conventional methods, a total of eight hours (two half days) are spent on forming, pouring and concreting. After the concrete has cured, the shaft frame and cover are applied. The employees then compact the remaining cavities with concrete. The wall thickness with this method is 20 centimetres.

In MOBBOT’s experience, it takes an average of between half an hour and an hour to install a 3D spray-printed wall reinforcement, including assembly of the shaft frame. This means that up to four shafts can be completed per day. The possibility of supplying wall reinforcements together with the associated shaft frames also offers savings potential in terms of transport routes.

The time required for excavation and restoration is comparable for the conventional and 3D methods. The printed wall reinforcement method requires a larger excavation (approximately twice the excavation for lateral backfilling and compaction). At the same time, MOBBOT says that shotcrete 3D printing uses around 25 per cent less concrete.

This method offers the greatest potential in rollout projects where several shafts have to be completed per week.

Teams of cablex technicians train Swisscom apprentices.

The Field Services team of technicians and Swisscom apprentices: a win-win project. Our ICT technicians in the field pass on their specific specialist knowledge, and the Swisscom apprentices help them with their daily work.

Portal neue Gubriströhre

cablex connects the tunnel infrastructure in Gubrist.

cablex realises the optical fibre expansion and signalling systems in the third gubrist tunnel.

One executive management team – eleven personalities.

Eleven people make up our executive management team. But how well do we actually know them? In our series "One executive management team - eleven personalities" we introduce you to the people who manage cablex.

Elektromobilität bei cablex

Testseite Release 22-06

Auf dieser Testseite sind alle neuen Elemente aus dem Release 22-06.

150 metres of optical fibre cable for "Zermatt unplugged".

A modern WLAN solution (Nimbra) was connected to the optical fibre connection.

In action for Colt for seven years.

Seven ICT technicians and two order managers meet customers' high demands.

Working for Sunrise with a new look.

Following the merger of Sunrise and UPC, a brand refresh has been carried out over the past year. The new clothes are now here, and our technicians have the new logo, which symbolises the sun rising, on their uniform.

DSC_796424-9.jpg

Taster days enquiry.

Are you interested in a career as

DSC_8480_24-9.jpg

Electrician EFZ.

No matter whether it's for electricity, telephony, Internet or television/radio in commercial or industrial buildings, you as an installation professional bring this nervous system in buildings to life!

Change of leadership in the Wireless PBX division.

A big thank you to Martin Müller, who is leaving cablex after eleven years to enjoy his well-deserved retirement.

Heating control with Swiss precision.

The building intelligence solution enables efficient heating control.

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444