Bagger 16-9

New hydraulic excavator in use.

The civil work activities at the Unterentfelden site have had a new mobile excavator since January. It was possible to put the vehicle, which has a lifting capacity of up to 1,500 kg, to immediate use in the excavation work undertaken as part of a sewer diversion. 

Carolin Rabea Primerova 1-1
16.02.2020
Author Carolin Rabea Primerova

New hydraulic excavator in use.

A sewer line in Kölliken runs right through four new building lots. For this reason, the municipality decided to move the line closer to the parcel boundary and the access road. The trenches in which the sewage pipes were to run again had already been excavated by the cablex Unterentfelden civil work team. The newly acquired hydraulic excavator was used to perform this work. The eight-tonne vehicle is roadworthy and equipped with the latest engine Technology.

The pipes have to be laid very precisely.

"The challenge in the construction of sewage systems is adhering to the pipe gradient," said Samuel Schaffner, Head of Department Network Planning & Construction. "The pipes have to be laid very precisely, so that the wastewater can flow away unimpeded," explains Schaffner.

Main sewer pipes are usually laid with a gradient of 0.5 to 2.4 per cent. The height of the inlet and the outlet is already set (by the previous course of the pipe).

After the diversion of the sewage system, the gradient of the line is only 1.03 per cent. This corresponds to a slope of 1.03 cm per metre.

Personen im Schacht 16-9

Alignment of the gradient.

The pipes have to be put into the trench with absolute precision in order to ensure that the pipe has a continuous gradient. Before the new sewer pipe is put into the trench, a layer of envelope concrete is put into the bottom of the trench.

Two concrete blocks serve as fixed points for the alignment of the gradient. The correct position of the blocks is determined using a laser measuring device.The audio signal of the laser indicates whether the concrete blocks are at the correct height. The longer the signal sounds, the more accurately the height of the block corresponds to the target. The envelope concrete bottom is aligned to the gradient with the concrete blocks as orientation.

Ausmessen 16-9

Proper alignment is also crucial for connecting the already laid pipe to the newly embedded pipe. Thanks to the correct position, the two pipe sections can be joined together. Before laying the pipe, it must be ensured that the inside of the pipe is clean. The rubber gaskets and the sleeve must be tight to withstand the pressure test that will be conducted later. For the pressure test, water is fed into the pipe, and the amount of water loss is measured.

Excavator operator with finesse.

Pipes of this size and weight are difficult to connect together manually. The hydraulic excavator is used by the excavator operator with a great deal of finesse to connect the inserted pipe to the already installed pipe. Here, the excavator has to apply pressure to the sewer pipe as accurately as possible in the alignment direction. The motto here is: "As little as possible, but as much as necessary." If the excavator operator exerts too much pressure on the pipe, he risks damaging the sleeve at the joint end. In this case, the next pipe cannot be connected.

To make matters worse, the shovel of the excavator has to operate in the excavator operator's blind spot. Seamless teamwork is called for here. The excavator operator must be able to rely on the instructions of his colleagues in the trench. Finally, the pipe is covered with envelope concrete. The concrete must harden sufficiently, so that it does not crack later.

Rohr 16-9
Schutzmatte 16-9

In cold weather, a protective mat is put on so the concrete does not freeze. Only a clean pipe bedding ensures that the pipe can later accommodate the pressure when the trench is filled. Once the diversion of the sewage system is complete, the manholes are constructed and the utility lines (e.g. electricity, telephone) are laid in the road, the road construction will be tackled. In this phase of construction, the granite edging is set, driveways are built and the asphalt layer is paved.

Zermatt 2024 - Hero 24-9

cablex job done – now the festival is on.

There are hardly any events or festivals in Switzerland that do not involve the cablex technician team.

Martina Strazzer 1-1
Martin mit Velo und seinem Vorgesetzten Markus an der Unfallstelle.

A bike ride with consequences!

A very personal story from the professional life of a cablex colleague.

Martina Strazzer 1-1
Headerbild PPS 3-4

Several teams with one goal: to rectify a fault.

Various departments work together from the time a fault is reported by the customer until it is rectified.

Larissa Mihalik 1-1
Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

Zwei cablex Servicetechniker vor dem Auto in Österreich

Hello, Austria

cablex service technicians install Internet and TV products and switch copper connections for A1 customers in Austria.

Martina Strazzer 1-1
24-9 Header Störunsteam

Our troubleshooting team takes to the road for a smooth-running network.

Every day, they ensure that network functionality is guaranteed. The Graubünden Troubleshooting Team rectifies around 700 faults per year.

Larissa Mihalik 1-1
Almer 3-4

We can carry out any technical installation with these glasses.

Whether it's the commissioning of a heating system or a water pipe or the installation of an alarm system – with the help of Almer glasses, our highly trained technicians can also install systems outside of cablex's core areas of work.

Larissa Mihalik 1-1
Beleuchtete Autobahn bei Nacht_24-9.jpg

Transport.

Creating a future-proof infrastructure with cablex.

emobility_19-24-9.jpg

smart cablex.

In our Smart Building, Smart City, Smart Construction and innovation, we implement innovative and forward-looking solutions for you.

Geschäftsleitungsmitglied, Pascal Sutter

It is "winning spirit" that determines whether you succeed or fail.

"Team sports, leadership and work teams have a lot in common," says Pascal Sutter, member of senior management.

Carolin Rabea Primerova 1-1
Techniker von cablex und viboo mit intelligenten Thermostaten

Everything as a Service (XaaS).

cablex is successfully implementing Everything as a Service.

Martina Strazzer 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444