Grossbaustelle in Schwamendingen

The watchful eye in the night.

One of the busiest roads in the Zurich area - with 120,000 vehicles per day - runs through the middle of a residential neighbourhood. The superstructure building activities along the 1.6-kilometre stretch of the N01/40 motorway has been ongoing since 2018. On behalf of FEDRO, under the main BSA construction management of INGE B2H (HDZ Elektroingenieure AG / Basler & Hofmann AG), cablex is responsible for the installation management of the operating and safety equipment (BSA) during the night shifts.  

Carolin Rabea Primerova 1-1
20.09.2023
Author Carolin Rabea Primerova

The term "enclosure" is used when a tunnel is created by enclosing a road in an open-cast working method with construction elements. The tunnels are not therefore created by drilling or blasting. The enclosure in Zurich-Schwamendingen will improve the quality of life in the neighbourhood through reduced noise pollution, less air pollution and more green and open spaces due to the newly created park on top of the enclosure.  

Installation management Schwamendingen enclosure.

The tasks of cablex. 

Alexandra Hoffman is one of nine cablex employees who have been assigned to the installation management team for this major project. The experience from large-scale projects like this one remains within the company and the knowledge is passed on internally, which benefits the customers of future projects. 

Statement Enos Pizio, Team Leader Infrastructure:  

"Entrusting cablex AG with installation management for the BSA activities was a very innovative approach on the part of FEDRO and the overall project manager Rolf Eberle. We appreciate the trust in allowing us to help shape such a complex project as the Schwamendingen enclosure (EHS), where the teams worked towards the common goal with a great deal of commitment and heart and soul. And that's exactly what our team does night after night. It gives us great pleasure and pride to be involved in such an important project for FEDRO and the city of Zurich, and to be able to support the entire EHS project team with their tasks". 

Rolf Eberle, Project Manager Federal Roads Office FEDRO says about the cooperation with cablex: 

"By adding cablex to our project team, we have gained a competent partner who will make an active and lasting contribution to the success of the project." 

The installation management tasks at a glance. 

Installation management of the main and subcontractors for the operating and safety equipment (BSA) during evening and night shifts includes, but is not limited to, the following activities: 

Checking the correct implementation of 

  • Energy supply 
  • Lighting 
  • Ventilation 
  • Signalling 
  • Monitoring systems 
  • Communication and control technology 
  • Cabling system (infrastructure) and ancillary facilities (doors and gates) 
  • Daily morning checks for the release of the road section and a system check to ensure there are no fault messages for the BSA sub-systems.
Portes ouvertes Header 24-9

Open house day - bienvenue à Penthalaz!

On 20 and 21 September, cablex opened its doors at the Penthalaz site to customers, partners, interested parties, employees and their families.

Larissa Mihalik 1-1
16-9 kopa

Plan construction projects sustainably and save costs.

Das Ziel ist, sich zukünftig mit anderen Unternehmen abzusprechen und die Rohre für Wasser, Energie und Telekommunikation in einem gemeinsamen Bauvorhaben zu realisieren.

Carolin Rabea Primerova 1-1
Wladimir Kiselew im Rosenbergtunnel

cablex handles complex switchovers in the Rosenberg tunnel.

Tunnel renovations are part of daily operations of the infrastructure segment of cablex AG. Cablex was responsible for the preliminary measures in the Rosenberg tunnel in St. Gallen.

Carolin Rabea Primerova 1-1
Beleuchtete Autobahn bei Nacht_24-9.jpg

Transport.

Creating a future-proof infrastructure with cablex.

Im Rahmen eines Pilotprojektes stattete cablex in den letzten Monaten Swisscom Zentralen mit Photovoltaikanlagen aus.

Customised photovoltaic expansion for Swisscom central offices.

As part of a pilot project, cablex has equipped Swisscom control centres with photovoltaic systems in recent months.

Carolin Rabea Primerova 1-1
Vier cablex Mitarbeitende vor Spleissbus

Major incident – working hand in hand until the network is up and running again.

On the weekend of 21 June, several debris flows occurred in the Misox valley in southern Graubünden following heavy storms. Our technicians report.

Carolin Rabea Primerova 1-1
Kornel Reutemann Mountainbike 3-4

From the Uetliberg to the roof: Kornel shows how smart energy works.

In this episode of the series "Insights – our management up close", we go on a mountain bike tour.

Larissa Mihalik 1-1
cablex Academy 24-9

cablex Academy.

The cablex Academy teaches specialist skills (competences) in the fields of network construction, service and installation. Here, focus is on the area of network construction for telecommunication.

Hero Smart Meter 24-9

Intelligent energy meters from smart cablex.

Smart meters make it possible to check electricity consumption remotely at any time

Greenfield 24-9

We were at Switzerland's biggest rock and metal festival.

This year's Greenfield Festival attracted around 84,000 visitors to Interlaken with top acts like Green Day, Bring Me the Horizon and The Prodigy.

Larissa Mihalik 1-1
Stefan Nünlist

Stefan Nünlist networks with employees and projects.

Stefan Nünlist's first few months in his new position were all about "meeting and greeting".

Carolin Rabea Primerova 1-1

cablex AG

Tannackerstrasse 7

3073 Gümligen

cablex.info@cablex.ch

0800 222 444